Planning Process
State Significant Development
The proposed Bondo Wind Farm project is considered to be a State Significant Development (SSD), which means that it will be assessed by the Department of Planning, Housing & Infrastructure (DPHI) in accordance with relevant planning policies and legislation.
Bondo Wind Farm is in the early stages of it’s development and is at the Environmental Impact Statement preparation Stage.
Please refer to the NSW DPHI’s website to learn more about the NSW SSD Planning Process.
Scoping Report
- A description of the land that the project is proposed on;
- A preliminary wind turbine layout;
- Information about the potential impacts and benefits of the project;
- Outcomes of preliminary desktop studies undertaken; and
- The outcomes of community and stakeholder consultation undertaken to date.
Secretary’s Environmental Assessment Requirements (SEARs)
NSW DPIH reviews the Scoping Report and issues a list of all the requirements that Neoen and specialist consultants must address, called the Secretary’s Environmental Assessment Requirements (SEARs). The SEARs include feedback from local Councils and Government agencies regarding these requirements.
The SEARs will inform the next stage of the project – the Environmental Impact Statement (EIS) for the proposed wind farm.
Environmental Impact Statement (EIS)
- Seasonal ecological surveys;
- Visual impact assessment;
- Noise impact assessment;
- Aboriginal Heritage assessment;
- Traffic and Transport assessment;
- Telecommunications
- Hazards, for example bushfire and flooding
- Aviation Safety